Atomstroiexport revises Turkey nuclear tender bid

Russia's Atomstroiexport, the only bidder in a tender to build Turkey's first nuclear plant, has revised its bid after initially offering to sell power at three times the current rate, Turkey's Energy Minister said.

Energy Minister Himli Guler told reporters on Monday that state power company Tetas was preparing a report on the revised offer from Atomstroiexport, which won the nuclear power licence tender with Turkish partner Park Teknik and Russia's Inter Rao.

Details of the new bid were not announced.

Atomstroiexport had offered to sell power at an average price of $0.2116 per kilowatt hour, Yasar Cakmak, head of state power company Tetas, told a news conference earlier in the day.

The average wholesale price in Turkey is about $0.079 per kilowatt hour. Atomstroiexport's bid would include covering its construction costs and a forecast for power prices over the life of the station, which could cost as much as $8 billion to build.

Turkey wants to build three nuclear plants to cover about 5 percent of the country's electricity needs and cut its reliance on energy imports. Its demand has been growing at a rate second only to China's.

Environmentalists and some economists say nuclear power is too expensive and could create health hazards in a country crisscrossed by earthquake faultlines.

The government took nearly three months to approve the Atomstroiexport bid after no other companies submitted bids in the September tender. It has pledged to revamp a nuclear-tender law to attract more interest before it holds other tenders.

Guler also said the government was preparing draft legislation that would allow for a second nuclear tender for a site along Turkey's Black Sea coast in the north.

Atomstroiexport's licence is to build a power station on Turkey's southern, Mediterranean coast that will have a capacity of about 3,000 to 5,000 megawatts.

(Source: Reuters)

Thursday, November 6, 2008

Turkey demands clarification in nuclear tender

The Turkish Atomic Energy Agency (TAEK) asked the Atomstroyexport-Inter Rao-Park Teknik joint venture, sole bidders in Turkey's first nuclear power plant tender, to clear some technical issues, the Anatolian Agency reported.

"We demanded an explanation when issues that required clarification regarding our security criteria occurred," a TAEK official told A.A. regarding their technical evaluation on the Russian-Turkish joint venture's proposal.

The tender held in September was disappointing given the fact that a number of foreign and local companies had previously expressed interest but did not submit bids.

The evaluations are complete, except for this issue, the official told AA adding that they would submit their decision whether the venture meet the required criteria to Energy Ministry until the end of November.

According to TAEK's criteria, nuclear power plantsmust meet updated and approved technological innovations and be compatible with international institutions criteria, including the International Atomic Energy Agency (IAEA).

The Akkuyu power plant on the Mediterranean coast in the southern province of Mersin has a planned capacity of 4,000 megawatts, plus or minus 25 percent.

(Source: Hurriyet)

Thursday, September 25, 2008

Sole bidder in Turkey's first nuclear plant tender Atomstroyexport

Turkey received six envelopes in the tender for the construction of the first nuclear power plant but only one of them was a bid, the general manager of Turkey's Electricity Trade Corp (TETAS) said Wednesday.

Haci Duran Gokkaya said Atomstroyexport-Inter Rao-Park Teknik joint venture is the sole bidder of the tender, adding the rest of the submitted envelopes were expressions of thanks.

“The competition process continues since we have a bid, and the final decision would be made by the tender commission,” Gokkaya told reporters when asked about whether the tender would be renewed or not.

He did not disclose the details of the bid and the proposal of the joint venture would be assessed by the commission for approval.

Suez-Tractebel, Atomic Energy of Canada Limited, Unit Investment N.V., Sabanci Holding's Ak Enerji and Hattat Holding-Hema were the other companies who submitted envelopes.

The company submitted three envelopes including letters for their bid. In the first envelope, which was opened on Wednesday, includes the application form, temporary assurances and other related documents mentioned in the tender file.

The second envelope consists of the documents showing the company meets the standards of the Turkish Atomic Energy Agency (TAEK) and the third envelope includes the production levels and the sale prices for the electricity that would be produced at the power plant.

The bid submitted by the Russian Atomstroyexport would be send to TAEK for the assessment. TAEK would make its evaluation on the second envelope submitted by the company and deliver its decision in two weeks.

In the third stage, the envelope that includes the price bid would be opened and the lowest bid would be submitted to the government for approval.

The Turkish government had expressed its commitment to nuclear energy despite opposition to the power plants over environmental and security concerns. Turkey’s previous three attempts for nuclear power plants had failed.

TETAS held its fourth tender for the construction of a nuclear power plant, which is expected to meet a minimum 8 percent of Turkey’s electricity generation by 2020, and 20 percent by 2030.

The Akkuyu power plant on the Mediterranean coast in the southern province of Mersin has a planned capacity of 4,000 megawatts, plus or minus 25 percent. The firm promising to sell the cheapest electricity to the state for 15 years would win the tender.

SUSPENSION POSSIBILITY
Foreign companies interested in the tender had previously demanded extra time and a suspension of the tender due to worsening global financial conditions. Experts had speculated that TETAS may suspend the tender if no company submits a bid.

On Monday Turkish Prime Minister Tayyip Erdogan ruled out the possibility of any suspension. Still experts had said it would not be surprising if no company bids for the tender and the process is suspended.

Companies such as Sabanci, General Electric, Hitachi Nuclear Energy and Spanish utility Iberdrola SA had expressed interest in the tender.

Firms taking tender documents had included Korean Electric Power Corp, Atomic Energy of Canada Limited, Japan's Itochu Corporation, France's Vinci Construction Grands Projets, Suez-Tractebel and Russian state firm Atomstroyexport

RISING PROTESTS
Around 500 nuclear protestors on Wednesday gathered in the Black Sea port city of Sinop to demonstrate the planned construction of Turkey’s second nuclear power plant in the region, Dogan News Agency reported.

"We do not want any nuclear power plants," the protestors said, criticizing the government and demanding an end to the process.

"The entire world knows that there is no safe way to store nuclear wastes. These plants create massive problems for the next generations and accidents can happen at these plants. Even if no accidents occur, those living in the vicinity of these plants have a more likely to develop cancer... This deadly tender should be ended," Dogan News Agency quoted one protestor as saying.

Turkish police had detained 34 activists in the capital Ankara during a peaceful nuclear protest against the bid process on Tuesday.

Police broke up the unauthorized protest in front of Turkey's energy ministry and detained the protesters, who had dressed in black and posed as dead bodies to highlight the dangers of nuclear power plants.

Turkey, which is a net importer of gas and oil, imports nearly 67 percent of its supply, a figure that is expected to reach 75 percent by 2020. In the next few years, the country's energy demand is set to rise by 8 percent annually.

(Source: Hürriyet, Turkey)

Wednesday, September 24, 2008

Turkey launches first nuclear power plant tender to meet energy demand

Turkey would hold a tender for the construction of its first nuclear power plant on Wednesday to reduce its dependence on foreign energy and to meet its increasing energy demand.

The Turkish government had expressed its commitment to nuclear energy despite opposition to the power plants over environmental and security concerns. Turkey’s previous three attempts for nuclear power plants had failed.

Turkey's Electricity Trade Corp (TETAS) will hold its fourth tender for the construction of a nuclear power plant in the Akkuyu region of the southern province of Mersin.

Turkey is planning to meet a minimum 8 percent of its electricity generation through the nuclear power plants by 2020, and 20 percent by 2030.

The Akkuyu power plant on the Mediterranean coast has a planned capacity of 4,000 megawatts, plus or minus 25 percent. The firm that promises to sell the cheapest electricity to the state for 15 years will win the tender.

TETAS will collect bids for the tender until 2:00 p.m. (1100 GMT) on Wednesday, and start opening bids at 2:30 p.m. (1130 GMT).

At the first phase of the tender, envelopes will be opened and the companies that meet the required conditions will be reported to the Turkish Atomic Energy Agency (TAEK) for approval. The envelopes, including the bid prices, will be opened following TAEK's thumbs up.

Suspension Possibility


Foreign companies interested in the tender had previously demanded extra time and a suspension of the tender due to worsening global financial conditions. TETAS may suspend the tender if no company submits a bid.

On Monday Turkish Prime Minister Tayyip Erdogan ruled out the possibility of any suspension. Still experts say it would not be surprising if no company bids for the tender and the process is suspended.

Companies such as Sabanci, General Electric, Hitachi Nuclear Energy and Spanish utility Iberdrola SA have expressed interest in the tender.

Firms taking tender documents also included Korean Electric Power Corp, Atomic Energy of Canada Limited, Japan's Itochu Corporation, France's Vinci Construction Grands Projets, Suez-Tractebel and Russian state firm Atomstroyexport.

Protests Against Tender

Turkish police Tuesday detained 34 activists during a peaceful nuclear protest against the bidding process.

The police broke up the unauthorized protest in front of Turkey's energy ministry and detained the protesters, the Anatolian Agency (AA) reported. The protesters, dressed in black, posed as dead bodies to highlight the dangers of nuclear power plants, AA added.

Turkey also plans to later build a second nuclear plant near the Black Sea port city of Sinop.

Turkey, which is a net importer of gas and oil, imports nearly 67 percent of its supply, a figure that is expected to reach 75 percent by 2020. In the next few years, the country's energy demand is set to rise by 8 percent annually.

(Source: Hürriyet, Turkey)

Monday, September 22, 2008

Turkey to hold tender for first nuclear power plant

The previous three tenders for the construction of a nuclear power plant failed.

Turkey will hold a tender to construct its first nuclear power plant on Wednesday.

Turkey's Electricity Trade Corp. (TETAS) will hold its fourth tender for the construction of a nuclear power plant in Akkuyu region of the southern province of Mersin on September 24th.

The previous three tenders for the construction of a nuclear power plant failed.

TETAS will continue collecting bids for the tender till 2 p.m. on Wednesday, and start opening bids at 2:30 p.m.

Turkish, Canadian, Japanese, French, Russian, South Korean, Chinese, Dutch and German firms are interested in the tender.

TETAS may extend the tender process in case firms do not submit bids for the tender. The firm that promises to sell the cheapest electricity to the state for 15 years will win the tender.

Turkey prefers building a nuclear power plant to reduce energy dependence on foreign countries and acquire the cleanest energy, and aims to raise the share of nuclear power plants in electricity generation to minimum 8 percent till 2020, and 20 percent till 2030.

Below are the thirteen companies that have received specifications for the tender so far.

-AECL Atomic Energy Of Canada Limited (Canada)
-Itochu Corporation (Japan)
-Vinci Construction Grand Projets (France)
-Suez Tractebel (France-Belgium)
-Atostroyexport (Russia)
-KEPCO (South Korea-Turkey)
-China Nuclear Power Components Co. (China)
-Unit Investment N.V. (The Netherlands)
-Haci Omer Sabanci Holding (Turkey)
-Alsim-Alarko Sanayi Tesisleri (Turkey)
-Hattat Holding (Turkey)
-RWE (Germany)
-Ak Enerji (Turkey)

(Source: World Bulletin)

Friday, July 25, 2008

Sabanci in Talks for Turkish Nuclear Power Plant Tender

Turkish diversified group Sabanci Holding has announced that it is in negotiations with GE, Hitachi Nuclear Energy and Iberdrola regarding a tender to construct and operate Turkey's first nuclear power plant, according to Reuters.

The news source reported that the Turkish government has set September 24, 2008, as the tender deadline for bids to build the nuclear power plant with capacity of around 4,000MW at Akkuyu on the country's Mediterranean coast.

Turkey is planning to build at least three nuclear power plants in a bid to reduce its dependence on energy imports.

Other prospective bidders include Atomic Energy of Canada, Itochu, Vinci Construction Grands Projets, Suez-Tractebel, Atomstroyexport and Korean Electric Power, according to the Turkish energy ministry.

(Source: iStockAnalyst)
tracking

Thursday, April 3, 2008

Turkey: Turkey Announces Its First Nuclear Generation Plant Tender

In response to predicted power supply shortfalls and rising oil prices Turkey has decided on the nuclear power option. Turkey wants to build three new nuclear generation plants with a total generation capacity of 5,000MW by 2015, the first of which will be developed at Mersin on Turkey's Mediterranean coast. The Mersin site was chosen as it already has the required license. Further down the line, a second nuclear generation plant will be located at Sinop on the Black Sea.

On 8 November 2007 the Turkish Parliament enacted the "Law on the Establishment and Operation of Nuclear Power Facilities and the Sale of Energy" (the Nuclear Law) which entered into force on 21 November. The Nuclear Law states that the procedure for the establishment of nuclear generation plants in Turkey will be determined by the Ministry of Energy and Natural Resources. The first tender for a nuclear plant will be organised by TETAS, the state-owned power wholesale company. The technical specifications and qualifications that companies must meet in order to take part in this tender were published by the Turkish Atomic Energy Institution (TAEK) on 21 December 2007.

(read more)

(Source: Mondaq)