Tuesday, November 3, 2009

safety concerns may delay third-generation nuclear reactor

[For those who do not follow the industry, digital I&C has been a focus item for nuclear regulators. There are several articles in the industry press on the conversion to digital in the US nuclear plants.]

http://www.topnews.in/safety-concerns-may-delay-thirdgeneration-nuclear-reactor-2231872

Paris - Nuclear safety authorities in France, Britain and Finland have issued a joint statement questioning the reliability of the new European Pressurized Reactor (EPR) currently being developed, the daily Les Echos reported Tuesday.

The statement raises concern over the reactor's command-control software which regulates its daily running and shuts it down in case of an incident. In its current state, the software cannot guarantee the necessary safety requirements, the report noted.

Potentially more problematic, the French nucear saftey authority ASN demanded that the French utilty EDF draw up an alternative plan for the EPR it will be running in the western French city of Flamanville.

According to Marcial Jorel, director of nuclear reactor safety at the Institute of Nuclear Safety and Radioprotection, "Either EDF takes our recommendations into account, or it must develop a new system, which will take years."

According to Les Echos, the Olkiluoto EPR nuclear power plant in Finland, which has already been delayed for three years and is scheduled to go online in 2012, may suffer an additional six-month delay because of the command-control problem.

French nuclear manufacturer Areva, which is building the Olkiluoto reactor, must now provide changes to its software and additional information by June of next year.

Both Areva and EDF said the concerns presented no unsurmountable problems.

"This is a process of step-by-step validation that is typical for projects of this kind. We have sufficient time to respond to the demands," Claude Jaouen, head of Areva's reactor division, told Les Echos.

However, the environmental group Greenpeace said the safety concerns expressed by the three authorities cast doubt over the entire industry.

"The nuclear industry is clearly showing its inability to manage the dangerous substances it manipulates and the waste it generates," Yannick Rousselet of Greenpeace France said Tuesday. "It is intolerable that the nuclear companies EDF and Areva continue their activities with impunity." (dpa)

Monday, September 14, 2009

UAE delays 41 bln dlr nuclear plants contract: report

http://www.zawya.com/story.cfm/sidANA20090914T075134ZCFJ39

DUBAI, Sep 14, 2009 (AFP) - The UAE has delayed awarding a 41 billion dollar contract to build nuclear power plants saying that the decision between the three rival bidders was too close to call, an Abu Dhabi daily said Monday.

"What happened ultimately was some of the bids were so close in some areas, we decided to proceed with all three," a senior government official told The National. "It will mean a slightly longer period of negotiations."

The decision on the contract, which was due to be awarded this Wednesday, will not come out until the end of the month, the newspaper reported, citing an unidentified diplomat.

A French group led by Areva, Electricite de France, GDF Suez and Total is competing against a Japanese-American alliance of Hitachi and General Electric, and a Korean-American consortium comprising Korea Electric Power, Samsung, Hyundai and US firm Westinghouse.

The Arab world's second-largest economy, the United Arab Emirates is seeking to reduce its dependence on hydrocarbons for power generation and to boost its image as an environmentally friendly country.

US President Barack Obama approved a civilian nuclear deal with the UAE in May.

Thursday, September 10, 2009

US Sen Boxer: Climate Bill To Include Nuclear-Power Measure

http://news.morningstar.com/newsnet/ViewNews.aspx?article=/DJ/200909091614DOWJONESDJONLINE000631_univ.xml

9-9-09 4:14 PM EDT | E-mail Article | Print ArticleWASHINGTON -(Dow Jones)- In a sign that compromise on energy and climate legislation is already underway, a top Senate negotiator said that she will include a measure on nuclear power in a developing bill, something that Republicans have demanded.


U.S. Senate Environment and Public Works Committee Chairman Barbara Boxer, D- Calif., who will be writing key parts of the climate bill, told reporters on Wednesday that "there will be a nuclear title in the bill." She had previously resisted any efforts to encourage nuclear power, saying before an August recess that nuclear power would already gain an advantage if the U.S. mandated reductions in greenhouse-gas emissions.

Republicans have encouraged nuclear power as a solution to climate change, saying that the near-zero emissions power plants are more reliable than renewable energy. Nuclear power is anathema to some environmentalists, partly amid concerns about how to dispose of nuclear waste.

-By Siobhan Hughes, Dow Jones Newswires; 202-862-6654; Siobhan.Hughes@ dowjones.com

Tuesday, September 8, 2009

China to Build More Nuclear Plants, Japan Steel Says

[A quick note that the AP-1000 reactors under construction in China will NOT have their vessels fabricated at JSW. News reports are that these vessels will be made by Doosan and then by the Chinese following technology transfer.]

http://www.bloomberg.com/apps/news?pid=20601101&sid=a7znRB.NvVmo

By Masumi Suga and Shunichi Ozasa

Sept. 7 (Bloomberg) -- Japan Steel Works Ltd., a maker of atomic reactor parts for Areva SA and Toshiba Corp., more than doubled its forecast for China’s nuclear plant construction because of stimulus spending and environmental pressures.

The country may build about 22 reactors in the five years ending 2010 and 132 units thereafter, compared with a company estimate last year for a total 60 reactors, President Ikuo Sato said in an interview. Japan Steel Works has the only plant that makes the central part of a large-size nuclear reactor’s containment vessel in a single piece, reducing radiation risk.

China, the world’s largest energy consumer after the U.S., is increasing spending on atomic energy as part of a 4 trillion yuan ($586 billion) economic stimulus and as it curbs greenhouse gas emissions. Japan Steel Works is counting on the rising reactor demand as the global recession curbs sales to customers such as carmakers and electronics companies.

“The potential for investment in nuclear power is huge,” said Shi Yan, an analyst at UOB-Kay Hian Ltd. in Shanghai. “Only a small number of companies in China have the right to develop nuclear power projects, but the country is open to foreign companies to help build reactors and to provide equipment.”

Japan Steel Works, which has lost 4.6 percent of its value this year, climbed 8.2 percent to 1,174 yen on the Tokyo Stock Exchange. The Nikkei 225 Stock Average rose 1.3 percent.

China became the world’s largest emitter of greenhouse gasses from burning oil and coal in 2006, followed by the U.S., Russia, India and Japan, according to U.S. Department of Energy data compiled by Bloomberg News.

Business Talks

“China, which had increased construction of coal-fired power plants, is now trying to focus on nuclear power because of the environmental issue,” Sato, 60, who took office in June, said in the Aug. 31 interview in Tokyo. “China is accelerating nuclear spending, and additional business talks are coming up.”

The country has 9,100 megawatts of nuclear capacity and has approved the construction of additional reactors able to generate 25,400 megawatts, Sun Qin, then-deputy head of the National Energy Administration, said last month. China will issue a plan by the end of the year to push development of clean energy sources such as nuclear, wind, solar and hydro power.

The average time it took to build China’s first 10 nuclear reactors was 6.3 years, according to a report commissioned by the German environment ministry.

Gross domestic product in China expanded 7.9 percent in the second quarter as the economy rebounded from the weakest growth in almost a decade, boosted by stimulus spending.

“Similar to road and railway construction, nuclear energy is also part of China’s plans for a recovery after the economy slowed,” Sato said.

Global Increase

Globally, a total of 52 nuclear reactors were under construction as of Jan. 1, according to the Japan Atomic Industrial Forum Inc. Last year was the first time in the history of commercial nuclear power that no new reactors came into operation, according to International Atomic Energy Agency figures. Some 33 new plants came online in 1984 and that number has declined almost every year since.

Japan Steel Works is spending 80 billion yen ($864 million) at its Muroran plant in the country’s northern island of Hokkaido by March 2012 to increase capacity to make parts for 12 nuclear reactors a year, compared with 5.5 units now, the president said.

The investment will increase annual sales from Japan Steel Works’ cast and forged steel for electric and nuclear power to 70 billion yen from the year starting April 2012, up from 45.5 billion yen expected for the current year, Sato said.

To contact the reporters on this story: Masumi Suga in Tokyo at msuga@bloomberg.net; Shunichi Ozasa in Tokyo at sozasa@bloomberg.net.

Last Updated: September 7, 2009 08:39 EDT

Monday, August 17, 2009

UAE and Japan - A Nuclear Family

An article in the Asia-Pacific Journal provides a detailed overview of the new nuclear power program in the UAE, the well-established nuclear power program in Japan, and the potential for Japanese vendors to play a key role in the UAE.

http://www.japanfocus.org/-David_Adam-Stott/3207

Thursday, June 11, 2009

Nuclear fusion power project to start in slimmed-down version

http://www.leaderpost.com/technology/Nuclear+fusion+power+project+start+slimmed+down+version/1678135/story.html

By Laurence Chabert, AFPJune 9, 2009

People look at tractors working on the future International Thermonuclear Experimental Reactor (ITER) site in Cadarache, southern France, in 2008. A multi-billion-dollar project to prove whether nuclear fusion, the power that fuels the Sun, can be a practicable energy source is to be scaled down in its early stages, sources said on Monday.Photograph by: Anne-Christine Poujoulat, AFPMARSEILLE, France – A multi-billion-dollar project to prove whether nuclear fusion, the power that fuels the Sun, can be a practicable energy source is to be scaled down in its early stages, sources said on Monday.


The test reactor, to be built at a site in southern France, will start its experiments in 2018 as scheduled but will initially be built in a slimmed-down form, they said.


"Discussions are underway about the best timetable," Catherine Cesarsky of France's Atomic Energy Commission (CEA) told journalists on the sidelines of a science conference here.


"There is a new commissioning strategy, a detailed discussion about the machine's deployment."


A decision approving the change will be put next week to the partners in the International Thermonuclear Experimental Reactor (ITER), she said.


Launched in 2006 after years of debate, the scheme aims at building a testbed at Cadarache, near Marseille, to see whether fusion, so far achieved in a handful of labs at great cost, can be a feasible power source.


Its seven backers are the European Union (EU), China, India, South Korea, Japan, Russia and the United States. Kazakhstan is poised to become the eighth member.


Nuclear fusion entails forcing together the nuclei of light atomic elements in a super-heated plasma, held in a doughnut-shaped chamber called a tokamak, so that they make heavier elements and in so doing release energy.


The process, used by the Sun and other stars, would be safe and have negligible problems of waste, say its defenders.


In contrast, nuclear fission, which entails splitting the nucleus of an atom to release energy, remains dogged by concerns about safety and dangerously radioactive long-term waste.


Cesarsky said the first experiments would begin on schedule in 2018 "but with a machine that will be less complete than initially thought."


"Technically, it is far more valuable to do the first plasma with an ITER that is not completely finished, because if there is a simple problem it can be detected."


A spokesman for ITER told AFP that the scaled-down version would entail using hydrogen initially.


Key experiments using tritium and deuterium, designed to validate fusion as a producer of large amounts of power, would not take place until 2026, the spokesman said.


This would be around five years later than previously scheduled.


The planned changes will be submitted to the ITER council, meeting in Mito, Japan, on June 17 and 18, he said.


The council will meet again in November to make a new assessment of costs, the official said.


Four years ago, ITER was priced at around 10 billion euros (13.8 billion dollars today), spread among its stakeholders, led by the EU, which has a 45-percent share.


Five billion euros (6.9 billion dollars) would go to constructing the tokamak and other facilities, and five billion euros to the 20-year operations phase.


Last month, the British science journal Nature said construction costs "are likely to double" and the cost of operations "may also rise."


If ITER is a success, the next step would be to build a commercial reactor, a goal likely to be further decades away.

© Copyright (c) Canwest News Service

Babcock & Wilcox planning mini nuclear reactor

http://www.sunherald.com/218/story/1404515.html

By DUNCAN MANSFIELD - Associated Press Writer

KNOXVILLE, Tenn. -- Babcock & Wilcox Co. announced plans Wednesday for a new class of mini nuclear reactors to be built in North American factories and shipped by rail to generating sites, and the Tennessee Valley Authority is evaluating what could become the first reactor location in Tennessee.

"This important project, we believe, will be a milestone in the nuclear renaissance," Brandon Bethards, CEO of Lynchburg, Va.-based B&W said during a teleconference from Washington.

The advanced light water reactor, named the "B&W mPower," represents "the harvesting of decades of nuclear manufacturing and design experience to provide a cutting-edge power generation source with emissions-free operation," he said.

The reactors will generate 125 megawatts - about one-tenth the size of a conventional commercial nuclear reactor - and offer several passive safety design features, including an underground containment that could accommodate storage for all of the spent fuel the reactor would use in a 60-year operating life.

A single reactor could power about 100,000 homes or a large factory. But more reactors can be added if needed.

The company plans to apply to the Nuclear Regulatory Commission for design certification by 2011 and have the first unit under construction by 2015 and powered up in 2018.

NRC spokesman Scott Burnell said B&W's licensing timeline is "not unreasonable, but at this point it is completely hypothetical." Other companies, including Toshiba, have discussed small reactors with the NRC, though none has submitted an application yet.

Burnell said the B&W design should contain many systems and technologies the NRC is familiar with in a standard pressurized water reactor. But building a reactor underground may require additional seismic analysis.

Knoxville-based TVA has signed a memorandum of understanding to assist the project by evaluating environmental conditions for a possible site for the first reactor. TVA nuclear executive Jack Bailey said TVA will examine a 1,300-acre site in nearby Oak Ridge where the scrapped Clinch River Breeder Reactor was to be built in the 1980s.

"I think you are coming into the market at the right time," said Sen. George Voinovich, R-Ohio, a longtime nuclear power advocate who hopes to see hundreds of manufacturing jobs created at B&W plants near Cleveland and Akron, as well as in Indiana, to build the reactor.

B&W expects to add up to 500 manufacturing and engineering jobs in the next few years in Ohio, Virginia, Indiana, Tennessee and possibly Canada just to get the reactor through design and licensing, said John Fees, CEO of B&W's Houston-based parent company, McDermott International.

Tennessee Sens. Lamar Alexander and Bob Corker, and Tennessee Reps. Lincoln Davis and Zach Wamp also gave their support during the teleconference.

Alexander, the Senate's third-ranking Republican, has proposed the United States build 100 nuclear reactors over the next 20 years - doubling the 104 now in operation - in response to global climate change and the need to reduce greenhouse gas emissions.

"My fellow Tennessean Al Gore, who has won the Nobel Prize for his campaign on the dangers of global warming, has a line he often uses about nuclear power - 'Nuclear may have a role to play, but unfortunately reactors only come in one size - extra large,'" Alexander said.

"Well, until today, Al Gore has been right," Alexander said, calling the mini reactor a new alternative. "Global warming may be the inconvenient problem, but especially after today, nuclear power is the inconvenient answer," he said.

TVA and Chicago-based Exelon Corp. will participate in an industry council advising B&W on the mini reactor. Exelon operates 17 reactors at 10 plants, while TVA has six reactors at three sites, is finishing a seventh reactor and planning up to four more.

"We believe the (mini reactor) has the potential to be game changing, yet is also practical and lower risk for the energy industry at a time when it is clearly in need of new solutions for a cleaner, more efficient future," said Craig Lambert, Exelon's vice president for nuclear engineering.

Friday, June 5, 2009

First wave or second wave for US nuclear projects?

I wrote an article for the June 2009 Nuclear Power International on the strategy being followed by US nuclear projects. Most projects are proceeding toward a potential first wave construction start, even though only a few (perhaps only those that get acceptable DOE loan guarantees) will actually start construction in the first wave.

Waiting until 2012 (when COL approvals should come) to decide to postpone a nuclear project may be much more expensive than moving to a thoughtful second-wave strategy now. Some companies, including Entergy and Ameren, seem to have decided to shift to the second wave already.

The article is at
http://pepei.pennnet.com/display_article/363984/140/ARTCL/none/none/1/First-Wave-or-Second-Wave?/

Thursday, June 4, 2009

China eyes Sanmen nuclear plant expansion end-2011

http://www.reuters.com/article/rbssConsumerGoodsAndRetailNews/idUSPEK32124420090604

Thu Jun 4, 2009 2:34am EDT

SANMEN, China, June 4 (Reuters) - China hopes to start building the next phase of its Sanmen nuclear plant by the end of 2011, the head of the project company said on Thursday. Sanmen in Zhejiang province, near Shanghai, is one of two sites in China where Westinghouse, a unit of Toshiba Corp (6502.T), and the Shaw Group (SGR.N) are building the first of their AP1000 reactors, so-called "third generation" nuclear plants.

The firms have started building the first phase -- two of a total planned six AP1000 reactors -- and expect it to start operating in 2013.

"There's some preparations and contracts to sign, but we hope to be launching construction of the second phase by the end of 2011," Gu Jun, general manager of China National Nuclear Corp Sanmen Nuclear Power Plant, told reporters at the site.

The consortium is building the plant under a technology transfer programme. China -- which wants to be in a position to build AP1000 reactors on its own by 2020 -- expects to complete the final phase without foreign help.

"We hope that units 5 and 6 will be built by ourselves," Gu said.

Westinghouse's AP1000 technology rivals the "third generation" design of Areva SA (CEPFi.PA), the European Pressurised Reactor, which is also being built in China.

Both firms are hoping their technology will become the favourite as countries across the world turn to nuclear as a reliable source of energy with low emissions.

China is leading the charge into nuclear power as it tries to wean itself off cheap but dirty coal. It has 11 working reactors capable of producing 9.07 gigawatts but wants to have 60-70 GW by 2020, about 5 percent of the total anticipated capacity.

As well as its two sites in China, Westinghouse says it has been picked to provide technology for 14 planned U.S. plants and last week said it would start talks with the Nuclear Power Corporation of India to deploy AP1000 technology there.

Areva's deputy president in China, Eric Neisse, told Reuters in an interview last month that Westinghouse's plants posed more risks than its own EPR. Its plant at Taishan in Guangdong province will be the third it has built, following projects in France and Finland. [ID:nPEK184789]

But Sanmen project manager Gu was confident about the AP1000.

"It's true that Areva's EPR is more mature than AP1000, but AP1000 has gone through a lot of R&D," he said.

"We have considered all factors: safety, cost, technology. And while there is some risk (in using untested technology), we believe the problems can be solved quickly during the construction process."

Thursday, May 14, 2009

White House names Gregory Jaczko US NRC chairman

http://platts.com/Nuclear/News/7866436.xml?sub=Nuclear&p=Nuclear/News&?undefined&undefined

Washington (Platts)--13May2009
President Barack Obama has named Commissioner Gregory Jaczko as chairman of the US Nuclear Regulatory Commission, the White House announced Wednesday.

Senate confirmation is not required because Jaczko is already a member of the commission.

Jaczko, a physicist who currently is the only Democrat on the presidentially appointed commission, will replace Dale Klein as chairman. Klein said early this year that he plans to serve out the remainder of his term -- ending in June 2011 -- as a commissioner if replaced as chairman.

Before joining the commission in 2005, Jaczko was science adviser to Senate Majority Leader Harry Reid of Nevada. Reid, a fierce opponent of the DOE high-level nuclear waste repository project at Yucca Mountain, Nevada, pushed for Jaczko's appointment to the commission in 2005. Jaczko's second term ends in June 2013.

"The industry expected this to happen," the industry official said of Jaczko's appointment. He said the industry will continue to work with Jaczko. "He has always had an open door," the official said.

One of the biggest issues the new chairman will have to deal with is the licensing of new reactors. In a keynote address at the NRC's Regulatory Information Conference in February, Jaczko expressed frustration that NRC?s new streamlined licensing process for new reactors wasn't operating as smoothly as had been envisioned.

Klein and Commissioners Pete Lyons and Kristine Svinicki are Republicans. No more than three members of any one political party can be appointed to the commission. One seat on the five-member commission is vacant. Lyons' first five-year term expires at the end of next month. Svinicki's first term ends in June 2012.
--Elaine Hiruo, elaine_hiruo@platts.com
--Steven Dolley, steven_dolley@platts.com