HELSINKI, Dec 31 (Reuters) - Franco-German consortium Areva-Siemens is to take TVO to arbitration in a dispute over delays and cost overruns at the Olkiluoto 3 reactor, the Finnish nuclear plant operator said on Wednesday.
In October, TVO was told by the consortium that the 1,600 MW reactor -- the first to be constructed in Western Europe for more than a decade -- would be further delayed to 2012 from its initial start-up target of 2009.
TVO claimed for compensation from the plant supplier consortium for losses and costs incurred due to the delay.
"The plant supplier, consortium Areva-Siemens, has filed a request for arbitration concerning Olkiluoto 3 delay and related costs," TVO said in a statement Wednesday.
"The request relates to a claim presented previously by the consortium to TVO, which TVO has studied and found to be without merit."
"TVO has a fixed price, turnkey contract with Areva-Siemens for the construction of the Olkiluoto 3 unit," TVO said.
TVO is owned by Finnish utility Fortum and Pohjolan Voima, a consortium of Finnish forestry and energy firms.
(Reporting by Sakari Suoninen; Editing by Mike Nesbit) Keywords: TVO/AREVASIEMENS/ (sakari.suoninen@reuters.com; +358 9 6805 0240; Reuters Messaging: sakari.suoninen.reuters.com@reuters.net)
Welcome to AtomWatch - world nuclear power news and analysis
This blog is aimed at tracing the world news related to nuclear power development internationally and in particular countries. Being an independent resource, we accept all kinds of opinions, positions and comments, and welcome you to discuss the posts and tell us what you think.
Wednesday, December 31, 2008
Subscribe to:
Post Comments (Atom)
1 comment:
Buy Kamagra
Cheap Kamagra
Buy Kamagra Cheap
Viagra Cialis
Cheap Viagra
Cheap Cialis
Viagra Cialis
Earn Google
Make Money on Google
M65 Jacket
M65 Field Jacket
Airline Dog Carrier
Airline Dog Carriers
Post a Comment